3. Your organization is beginning a new project staffed with a virtual team that is located in five countries worldwide. Based on experience, you recognize that team members in a matrix environment sometimes will be more responsive to their functional manager than to you, their PM. Anticipating these problems, you decide to prepare a A. Memo to team members informing them that they work for you now B. Project charter C. Memo to functional managers informing them that you have authority to direct their employee D. Human resource management plan. Answer is B. but project charter 不是高级经理发出的吗?PM 无权准备project charter 吧。
其实关键还是要仔细的看PMBOK的原文,特别是英文版本的原文.从题目的意思看,这个是关于项目经理的权限问题,项目经理的权限显然是Project Charter里面规定的,书上的原文说the project charter providers the project manager with the authority to ....至于你说的ProjectChater谁来发出,书上的本意是说这个"批准"最好是有高级经理来做,至于Prepare的话应该是Project Team